Concrete Batch Plants Cylinder Malfunction

Brief Introduction:Cylinder cushioning effect is poor generally due to buffer ring wear or damage. This should replace the sealing ring and adjusting screw.

One of the Concrete batch plants gas system malfunction is cylinder malfunction. Which is the specific aspects have?

1. Cylinder external leakage or internal leakage , usually due to piston rod installation eccentric , lack of oil supply, seal rings wear or damage, there are impurities in the cylinder and the piston rod caused by scars and so on. Should be re-adjusted the central position of the piston rod, the need to regularly check the reliability of the oil mist, timely removal of impurities in the cylinder; 

2. Cylinder output force is not enough and the action is not smooth, usually due to the piston or piston rod is stuck, poor lubrication, lack of air supply, or cylinder with condensed water and impurities. The center of the piston rod should be adjusted; check the reliability of the work of the oil mist; air supply pipe is blocked, the cylinder should be promptly removed condensate and impurities.

3. Cylinder cushioning effect is poor generally due to buffer ring wear or damage. This should replace the sealing ring and adjusting screw.

4. Piston rod and cylinder head is damaged, usually due to eccentric piston rod or buffer mechanism does not work. This should be promptly adjust the piston rod center position, if necessary, replace the buffer seal ring or adjustment screw.